Project Description
Air Conditioning – Central Plant Upgrade
Work completed to upgrade the Keith Burrows & Physics Theatres air-conditioning plant
- Complete demolition and removal of the chiller and boiler plants
- Provide new 2 x Modulex boilers
- Provide new primary & secondary HHW reticulation systems
- Provide new 3 x HHW secondary field pumps
- Provide new 2 x HHW primary boiler pumps
- Provide new 1 x air cooled Carrier chiller
- Provide complete new Chilled water reticulation system complete with new 2000 litre buffer tank
- Provide new 2 x CHW pumping station
- Upgrade the Electrical switchboard and new VSDs to all new pumps
- Provide complete new BMCS